Construction of Motorable Bridge presstress Concerete bridge at Dhungri Khola(Chainage : 33+500) at District palpa and Arghakhachi along Saljhandi Sandhikharka Dhorpatan Road Project
  • The road works was started in 3/30/2072 and completed in 05/30/2075.
  • Employee: Saljhandi-Sandhikharka-Dhorpatan Road Project
  • Salient Features of the projects:
    The project has been awarded to the The Kanchanjunga – Motidan JV.
    The project work comprises of Cast in Situ, 2 webbed Pre stress Concrete Slab Deck, RCC Cantilever Type & RCC open Foundation.
  • Contract Amount: NRS. 4,01,19,135.63
Construction of 25.0m Simply Supported, Cast in-situ 2-Webbed Reinforced Concrete Bridge over Bangi Khola at Aateha Sanhu, Arghakhanchi Contract ID: DROSPR/3371574/075/076-034
  • The road works was started in 3/30/2073 and completed in 3/30/2077.
  • Employee: North South Koshi Road Project, Khadbari, Sankhusubawa
  • Salient Features of the projects:
    The project has been awarded to the The Kanchanjunga – Gajurmukhi – Motidan JV
    The project work comprises of earthwork excavation in all kinds of soil and structure and drains, RCC Hime Pipe laying, retaining structure works of masonry/gabion works, road side earthen drain, subgrade works, subbase works etc.
  • Contract Amount: NRS 57,34,25,691.23