Upgrading of Mechi-Ratuwa Road, Jhapa ( 19+000 to 33+900)
Agreement Date: 7/24/2076
Completion Date: 3/31/2080
Value (With VAT) : NRs. 81,62,00,946.19
Agreement Date: 7/24/2076
Completion Date: 3/31/2080
Value (With VAT) : NRs. 81,62,00,946.19
A7400456DSC00351

Work ​Description

Contract ID: HRP/3372244/075/076-UR-013

  • Earthworks excavation for foundation -30,506.60 cum
  • Dry stone soiling -5,060.71 cum
  • Cement concrete M15/40-5,229.91
  • Brick masonry workss(1:4)-9,185.01 cum
  • Plun concrete works (60%M15 concrete & 40% boulder/stones)-26,536.72 cum
  • Gabion works -12,044.50 cum
  • Cement oncrete M20/20-397.19 cum
  • Cement concrete M25/20-1,600.27 cum
  • Reinforcement-157.01 MT
  • Formworks -69,121.71 sqm
  • Sub grade works -100,033.00 sqm
  • Embankment works-3,08,469.59 cum
  • Sub base works -34,878.79 cum
  • Base course works-18,339.29 cum
  • Prime coat works -82,456.44 Ltr
  • Tack coat works-99,785.35 Ltr
  • Bituminous works -dense bitumunous macadam works-5,382.63 cum
  • Bituminous works-Asphalt concrete works-3,726.17 cum

Name of​ Client & Contract Person

  • Postal Highway Directorate, Project Office Itahari,Sunsari

Joint ​ Venture

Name of JV  :
  • P.S
  • Gajurmukhi
  • Motidan
JV Share
0%
  • Roadway excavation Ina types o soil including rock-79,676.07 m3
  • NP3 Humpipe 900mm dia supply and laying Works-55.OO Rm
  • Gabion works- 11104.75
  • RRM works-1,643.36 m3
  • Saljhandi-Sandhikharka-Dhorpatan Road Project
Name of JV  :
  • M/S. Motidan Construction Sewa Pvt. Ltd.
My Skill
Web Designer 50%
Project Details

Roadway Excavation , Hume pipe culvert,Gabion/Masonary wall construction , side drain and Graveling works (Chainage 0+000 to 5+300)