Road Widening and Improvement Works of Kulekhani-Sisneri-Chhaimale-Dakshinkali Road (Working Sector Sisneri to Kulekhani CH 21+000 to 26+800)
Agreement Date: 3/30/2074
Completion Date: 12/30/2078
Value (With VAT) : NRs. 16,78,67,380.78
Agreement Date: 3/30/2074
Completion Date: 12/30/2078
Value (With VAT) : NRs. 16,78,67,380.78
Work Description
Contract ID: DROHTD/337305-4/073-74/204
- Roadway excavation in all types of rocks and soils -69020.27 cum
- Formation of embankment including compaction-10204.50 cum
- Gabion works for retain wall, brest wall cheek dam-9158.50 cum
- Plum concrete with 60% M15/40 concrete and 40% boulders/ stones-3221.09 cum
- PCC M15/40-440.81 cum
- RRM work in 1:4 C/S morter -4135.65 cum
- Providing and laying of plain cement concrete M20-93.00 cum
- Providing and laying fitting and placing un- coated mild steel/HYSD reinforcement complete -4.82 MT
- Laying of single/doble/muliple bituminous coats for surface dressing (DBST) first coat-497.20 MT
- Laying of single/doble/muliple bituminous coats for surface dressing (DBST) second coat-552.33 MT
- Provide and erecting “W” metal beam crash barrier-3695.00 RM
Name of Client & Contract Person
- Infrastructure Development Office, Makwanpur, Chitwan
Joint Venture
Name of JV :
- Motidan
- Gajurmukhi
JV Share
0%
- Roadway excavation Ina types o soil including rock-79,676.07 m3
- NP3 Humpipe 900mm dia supply and laying Works-55.OO Rm
- Gabion works- 11104.75
- RRM works-1,643.36 m3
- Saljhandi-Sandhikharka-Dhorpatan Road Project
Name of JV :
- M/S. Motidan Construction Sewa Pvt. Ltd.
My Skill
Web Designer
50%