Upgrading/Improvement of Baddichaur-Gutu-Karnali (Km 23+340 to 45+300 0+000) section of Madan Bhandari Highway (NH09) to Blacktop Standard
Agreement Date: 23/05/2078
Contract End Date: 11/17/2082
Value (With VAT) : NRs.1214.93
147500990_274250527381484_6179895529777018010_n-2-2Smart-light

Contract No.

  • MBHPD/337011084/079/80-007

Name of​ Client & Contract Person

  • Government of Nepal , Ministry of Physical Planning and Transport,Department of Roads ,Madan Bhandari Highway Project Directorate

Progess

Completed Work
0%
Physical Progess
0%
  • Roadway excavation Ina types o soil including rock-79,676.07 m3
  • NP3 Humpipe 900mm dia supply and laying Works-55.OO Rm
  • Gabion works- 11104.75
  • RRM works-1,643.36 m3
  • Saljhandi-Sandhikharka-Dhorpatan Road Project
Name of JV  :
  • M/S. Motidan Construction Sewa Pvt. Ltd.
My Skill
Web Designer 50%
Project Details

Roadway Excavation , Hume pipe culvert,Gabion/Masonary wall construction , side drain and Graveling works (Chainage 0+000 to 5+300)