Upgrading of Bhadrapur-Phadanipul-Itabhatta-Bouddhamod-Salakpur Road,Jhapa
Agreement Date: 23/05/2078
Contract End Date: 23/05/2080 (on process of EOT till 2081/5/23)
Value (With VAT) : NRs.280
433679502_735123215478119_688378571054801516_nmaxresdefault

Contract No.

  •  IDOJHP/NCB/W-67/076/77

Name of​ Client & Contract Person

  • IDO Jhapa

Progress

Completed Work
0%
Physical Progress
0%
  • Roadway excavation Ina types o soil including rock-79,676.07 m3
  • NP3 Humpipe 900mm dia supply and laying Works-55.OO Rm
  • Gabion works- 11104.75
  • RRM works-1,643.36 m3
  • Saljhandi-Sandhikharka-Dhorpatan Road Project
Name of JV  :
  • M/S. Motidan Construction Sewa Pvt. Ltd.
My Skill
Web Designer 50%
Project Details

Roadway Excavation , Hume pipe culvert,Gabion/Masonary wall construction , side drain and Graveling works (Chainage 0+000 to 5+300)