Construction of Road Structure from Nigali (35+000) to Pali (54 + 000) section of Saljhandi -Sandhikharka -Dorpatan Road
Agreement Date: 1/20/2074
Completion Date: 8/15/2074
Value (With VAT) : NRs. 1,75,04,255.29
Agreement Date: 1/20/2074
Completion Date: 8/15/2074
Value (With VAT) : NRs. 1,75,04,255.29
C9502.00_27_29_47.Still028C9502.00_27_54_05.Still029

Work ​Description

Contract ID: SSDRP/3371204/073/074-010

  • Masonry works-1013.89 m3
  • Gabions works-2889.00 m3

Name of​ Client & Contract Person

  • Department of Road, Saljhandi Sandhikharka Dhorpatan Road Project,Sandhikharka, Arghaghanchi

Joint ​ Venture

Name of JV  :
  • Motidan
  • PTR
JV Share
0%
  • Roadway excavation Ina types o soil including rock-79,676.07 m3
  • NP3 Humpipe 900mm dia supply and laying Works-55.OO Rm
  • Gabion works- 11104.75
  • RRM works-1,643.36 m3
  • Saljhandi-Sandhikharka-Dhorpatan Road Project
Name of JV  :
  • M/S. Motidan Construction Sewa Pvt. Ltd.
My Skill
Web Designer 50%
Project Details

Roadway Excavation , Hume pipe culvert,Gabion/Masonary wall construction , side drain and Graveling works (Chainage 0+000 to 5+300)