Road widening and improvement works at Aale Bhanjyang-Baguwa Road Sector (Chainage: 40+300 to 51+000 KM)
Agreement Date: 5/25/2071
Completion Date: 2/25/2075
Value (With VAT) : NRs. 7,80,05,756.57
Agreement Date: 5/25/2071
Completion Date: 2/25/2075
Value (With VAT) : NRs. 7,80,05,756.57
DSC00361A7400472

Work ​Description

Contract ID: KANTILTP/3371064/070/071-007

  • Back Cutting/Grad Cutting Work-2,30,973.20 m3
  • Embankment Filling-27,077.40 m3
  • Clearance of Landslide-13,522.48 m3
  • Sub-Grade Work-56.873.00 m3 Sub Base Course works-9,045.70 m3
  • Stone Masonry works with cement mortar-4,454.53 m3
  • Gabion work-6,00.50 m3
  • Concrete work(M15/40)-266.81 m3
  • Hume pipe works(600mm and 900mm internal duameter-425.50 Rm
  • Plum Concretr withM15/40 works-228.23 m3

Name of​ Client & Contract Person

  • Kantilokpath Road Project, Lalitpur

Joint ​ Venture

Name of JV  :
  • S.C.C
  • Motidan
JV Share
0%
  • Roadway excavation Ina types o soil including rock-79,676.07 m3
  • NP3 Humpipe 900mm dia supply and laying Works-55.OO Rm
  • Gabion works- 11104.75
  • RRM works-1,643.36 m3
  • Saljhandi-Sandhikharka-Dhorpatan Road Project
Name of JV  :
  • M/S. Motidan Construction Sewa Pvt. Ltd.
My Skill
Web Designer 50%
Project Details

Roadway Excavation , Hume pipe culvert,Gabion/Masonary wall construction , side drain and Graveling works (Chainage 0+000 to 5+300)