Other Works
Construction of Motorable Bridge presstress Concerete bridge at Dhungri Khola
Chainage : 33+500) at District palpa and Arghakhachi along Saljhandi Sandhikharka Dhorpatan Road Project
The road works was started in 3/30/2073 and completed in 3/30/2077.
Employee: North South Koshi Road Project, Khadbari, Sankhusubawa
The project work comprises of earthwork excavation in all kinds of soil and structure and drains, RCC Hime Pipe laying, retaining structure works of masonry/gabion works, road side earthen drain, subgrade works, subbase works etc.
Contract Amount: NRS 50,05,10,653.89
The road works was started in 3/30/2073 and completed in 3/30/2077.
Employee: North South Koshi Road Project, Khadbari, Sankhusubawa
The project work comprises of earthwork excavation in all kinds of soil and structure and drains, RCC Hime Pipe laying, retaining structure works of masonry/gabion works, road side earthen drain, subgrade works, subbase works etc.
Contract Amount: NRS 50,05,10,653.89
Construction of Motorable Bridge presstress Concerete bridge at Dhungri Khola(Chainage : 33+500) at District palpa and Arghakhachi along Saljhandi Sandhikharka Dhorpatan Road Project
- The road works was started in 3/30/2073 and completed in 3/30/2077.
- Employee: North South Koshi Road Project, Khadbari, Sankhusubawa
- Salient Features of the projects:
- The project has been awarded to the Gajurmukhi-Motidan-Geetanjali JV
- The project work comprises of earthwork excavation in all kinds of soil and structure and drains, RCC Hime Pipe laying, retaining structure works of masonry/gabion works, road side earthen drain, subgrade works, subbase works etc.
- Contract Amount: NRS 50,05,10,653.89